Built for a data-center electrical contractor, for a data-center operator in Mexico
Aug 2026 – Dec 2026 an eight-figure program
Units
Product
Amperage
Voltage
Bus
Enclosure
Interrupting rating
Breakers
Planned shipments
Built in
In Mexico, a data-center operator is bringing data-center capacity online in stages, and each stage’s installation needs its remote power panels on site. The first order from a data-center electrical contractor covered one stage with 48 panels. The second covered eight more stages with 768 panels at 415Y/240V, scheduled to ship in batches of about 70 as panels come off the line rather than held for one delivery.
Every panel is a 400A main-breaker, 42-circuit RPP at 415Y/240V, three-phase four-wire, in a NEMA 1 enclosure with tin-plated copper bus. Each carries a Siemens 3VA 400A LSI main, 100% rated at 35 kAIC, and fourteen 3-pole branch breakers rated 25 kAIC filling its 42 circuit positions. A branch-circuit monitoring system with split-core CTs on all 42 branch conductors and on the main reports current to a local display. The first order uses 60A branch breakers; the 768-panel order steps up to 100A.
| Qty | Item | Rating | Voltage | Enclosure | Bus | Notes |
|---|---|---|---|---|---|---|
| 48 | Remote power panel | 400A MCB, 42 circuits | 415Y/240V 3Ø 4W | NEMA 1 | Copper, tin-plated | Fourteen 60A 3-pole branch breakers; branch-circuit monitoring |
| 768 | Remote power panel | 400A MCB, 42 circuits | 415Y/240V 3Ø 4W | NEMA 1 | Copper, tin-plated | Fourteen 100A 3-pole branch breakers; branch-circuit monitoring |
Engineered, fabricated and assembled under one roof in Jurupa Valley, California.
As of September 2026 the 48-panel order is at the ready-to-ship stage, with shipment projected for October 2026, and the 768-panel order is in assembly. DEI’s delivery schedule splits the large order into two phases of 384 panels: the first window runs October–November 2026, the second November–December 2026. Completed panels are to ship as they come off the line, in planned batches of about 70, so installation does not wait for a whole phase.
Status as of September 2026, from DEI’s build records.
From DEI’s submittal, Jul 2026
| Qty | Item | Rating | Voltage | Enclosure | Bus | Notes |
|---|---|---|---|---|---|---|
| 48 | Remote power panel | 400A MCB, 42 circuits | 415Y/240V 3Ø 4W | NEMA 1 | Copper, tin-plated | Fourteen 60A 3-pole branch breakers; branch-circuit monitoring |
From DEI’s submittal, Aug 2026
| Qty | Item | Rating | Voltage | Enclosure | Bus | Notes |
|---|---|---|---|---|---|---|
| 768 | Remote power panel | 400A MCB, 42 circuits | 415Y/240V 3Ø 4W | NEMA 1 | Copper, tin-plated | Fourteen 100A 3-pole branch breakers; branch-circuit monitoring |
6 RPP orders from one contractor
600A, 400A and 300A remote power panels, six orders in four months, released one project at a time; one order left as a single truckload of about 35,000 lb.
Jun 2026 – Jan 2027
Metered 400A RPPs delivered, then a direct follow-on order
Metered 400A RPPs, then PDU metering boxes and 480V distribution panels ordered direct by the facilities manager.
Jul 2026 – Nov 2026
24 RPPs with branch-circuit monitoring
400A, 208Y/120V remote power panels with copper bus, for a colocation provider in the Southeast U.S.
Sep 2026 – Nov 2026
Company names identify who DEI’s orders are for. Their use does not imply endorsement of DEI.
Dates, quantities and turnarounds as of September 2026, from DEI’s build and order records. Images are representative unless marked otherwise.